Grace Camp - Sumy Ukraine

Hall Expansion Project 2008 - 2011
What the building looked like up to February 25, 2008

The building at present can only facilitate groups of a maximum of 20 people.  With an expansion and renovations, the building will be able to be used year round:

  • For groups of 30-50 people
  • For rentals year round which can be completely self contained within the building (meeting area, eating area, sleeping area & washroom facilities)
  • The meeting area will also facilitate summer programming, adding extra meeting space for different activities and/or space for inclement weather activities.
  • It also provides the option of renting the camp to more than one group at a time because of the facilities that are available.
Addition would provide:
  • Sleeping area for approximately 30-50 people
  • Extra toilets and showers
  • Meeting & eating space on main floor for 30-50 people
The building would be usable 12 months of the year as it is already winterized, with gas and water hooked up.

Timeline
Questions?  Contact me
Want to participate?  Print this donation form and mail it to SEND International.  All donations are tax deductible.
Paetkau's Place
Project Update
Floor plans
Old & New
What the building looked like in October, 2010

Praise the Lord! 

Changes are taking place on the inside & outside....
see stage 2 updates for more information

February 2008
  • Begin with construction as the weather holds
  •  Get the outer walls up and a roof on so that the site is closed to the weather
March 2008
  • Begin renovations on the second floor interior of the building

Summer 2008
  • put down subfloor
  • frame in upstairs
  • run plumbing and electric
  • hang drywall

Fall 2008
  • build entrance
  • install front entrance windows and main front         windows

Spring & Summer 2009
remove flooring on main floor and fill in crawl space
pour first layer of cement

Fall 2009
install new windows on main floor
plaster a portion of the interior walls
frame and drywall remaining interior walls and ceilings

Winter 2009
pour layer of cement on main floor
lay tile on main floor

Fall  & Winter 2010/2011
complete preparing drywall throughout and painting on both floors
begin installing bathrooms in upstairs

install kitchen on main floor
install permanent light fixtures throughout